Dated sample — current status is not verified. This record is held from current briefings because its source may have changed, its check may be incomplete, or verification may have expired. The saved facts and qualifications below describe the stated review dates. Check the original source before acting.

Contract enteredCarlisle · North West

C76 Durranhill Viaduct C1045 - Remedial Works (Phase 2)

A UK7 notice confirms Metcalfe Plant Hire’s signed phase-two remedial contract. Cumberland Council says physical works are due to begin on 28 September, with weather-dependent completion in February 2027; this differs from the notice’s contract period.

01 / Project assessment

Why this project is relevant

Assessment: the civil works are real, but the contractor itself operates a substantial hire fleet. Treat this as a programme watch or specialist/overflow prospect, not a general plant-hire lead.

Tools & small plantPowered accessSite welfare

These are the hire categories YardBrief has matched from the published project scope.

02 / The source facts

What is happening

  • Expansion-joint replacement and waterproofing
  • Carriageway and footway resurfacing
  • Vegetation clearance and local masonry/parapet repairs
  • Works on Eastern Way over the railways in Carlisle
Named contractor / developer
METCALFE PLANT HIRE LIMITED ↗
Company 02093086
Project stage
Contract entered
Published contract value (ex VAT)
£495,314.80
Source contract / programme start
17 Aug 2026
Source notice
UK7 · 085844-2026
Notice published
10 Sept 2026
Last updated
61 days ago
03 / Before you contact them

Check these points

  • UK7 records signature on 15 August and a contract period of 17 August to 18 December 2026.
  • The council’s 7 September operational update instead gives site work from 28 September, Christmas break, return on 4 January and completion in February 2027, weather dependent. Dates require reconciliation.
  • Metcalfe’s own site states it offers more than 500 plant items. Its own fleet reduces the case for external general hire.
  • £495,314.80 excluding VAT is phase-two contract value, not phase-one cost or equipment spend.
  • No project-specific open equipment enquiry or unsatisfied hire requirement has been verified.